Mr Mustard has written about vanity awards before and last year he did some follow up enquiries to see if there was any correlation between free dinners and work for suppliers.
20 July 2012
Dear Barnet Homes
Go Awards - Birmingham Metropole- March 2012
Four staff and two residents attended.
Did the hotel cost include the cost of the dinner? (my
experience is that these dinners often cost £90 a head)
How much was the dinner and who paid for it please?
Yours sincerely
Mr Mustard
20
August 2012
Dear Mr
Mustard
The
hotel cost did not include the cost of the dinner. The dinner for the Barnet
Homes staff and residents who attended the event was paid for by echelon
Consultancy, which had facilitated the procurement process and with which the
award entry had been compiled.
This is
recorded in the Barnet Homes register of gifts and hospitality, with an assumed
cost of £80 per head. We do not have a record of the actual costs incurred by
echelon Consultancy for the dinner.
Yours
sincerely
Barnet
Homes
20 August 2012
Dear Barnet Homes
Thank you for that answer.
I have a new question please.
Please provide a list of all payments made to Echelon since
1 April 2006 ( date, amount & what for ) and a copy of all contracts signed
with them since the same date.
Please also provide a copy of the register of gifts and
hospitality for the year ended 31 March 2012.
Yours sincerely
Mr Mustard
18
September 2012
Dear Mr
Mustard
Please
find following the response to your enquiry below.
1.
Payments to Echelon
Echelon
delivered a number of different projects and services associated with Barnet
Homes’ procurement and mobilisation of repairs and maintenance contractors
through nine lots. The total value of the contracts, based on the ten years
covered, exceeds £200million.
i)
Strategy works:
Date
|
Amount
(excl VAT)
|
Area
of work
|
24/06/2010
|
£5312.21
|
Strategy
works
|
24/06/2010
|
£5327.90
|
Strategy
works
|
29/07/2010
|
£1375.00
|
Strategy
works
|
27/08/2010
|
£732.00
|
Strategy
works
|
26/10/2010
|
£1082.00
|
Strategy
works
|
Subtotal:
£13,829.11
Following
a competitive quotes process, Echelon was commissioned to draft a strategic
asset management procurement strategy for Barnet Homes. The costs also included
a workshop with Barnet Homes staff and a workshop with residents who had
expressed an interest in being involved in the procurement process.
ii)
Procurement process
Date
|
Amount
(excl VAT)
|
Area
of work
|
30/11/2010
|
£4089.00
|
Procurement
|
23/12/2010
|
£6977.00
|
Procurement
|
28/01/2011
|
£5237.00
|
Procurement
|
15/02/2011
|
£16343.00
|
Procurement
|
14/03/2011
|
£9448.00
|
Procurement
|
20/04/2011
|
£22834.20
|
Procurement
|
26/05/2011
|
£8673.30
|
Procurement
|
24/06/2011
|
£6972.00
|
Procurement
|
09/08/2011
|
£3354.20
|
Procurement
|
13/09/2011
|
£5036.00
|
Procurement
|
21/10/2011
|
£1065.00
|
Procurement
|
23/11/2011
|
£3505.00
|
Procurement
|
Subtotal:
£93,533.70
Echelon
oversaw the procurement process for all nine asset management contracts. It is
standard practice to use an external agency for procurement of this scale. Work
included overseeing the procurement model, contract documentation, facilitating
evaluation of PQQs, cost evaluation, feedback to senior management and the
Barnet Homes board, more than 40 onsite interviews and inspections, tender
clarification and the appointment of contractors.
iii)
Mobilisation – Project Management
Date
|
Amount
(excl VAT)
|
Area
of work
|
17/08/2011
|
£6825.00
|
Mobilisation
PM
|
13/09/2011
|
£9750.00
|
Mobilisation
PM
|
17/10/2011
|
£5850.00
|
Mobilisation
PM
|
23/11/2011
|
£8125.00
|
Mobilisation
PM
|
13/01/2012
|
£5850.00
|
Mobilisation
PM
|
23/01/2012
|
£10400.00
|
Mobilisation
PM
|
22/02/2012
|
£9750.00
|
Mobilisation
PM
|
19/03/2012
|
£9750.00
|
Mobilisation
PM
|
13/04/2012
|
£10400.00
|
Mobilisation
PM
|
18/05/2012
|
£9100.00
|
Mobilisation
PM
|
15/06/2012
|
£650.00
|
Mobilisation
PM
|
Subtotal:
£86,450
Echelon
supplied a project manager to oversee the mobilisation of the nine contracts.
This was agreed following a benchmarking exercise. Costs are based on an agreed
day rate of £650.
iv)
Mobilisation – IT consultancy
Date
|
Amount
(excl VAT)
|
Area
of work
|
12/12/2011
|
£6320.00
|
Mobilisation
IT
|
13/01/2012
|
£3860.00
|
Mobilisation
IT
|
29/02/2012
|
£7800.00
|
Mobilisation
IT
|
23/03/2012
|
£7150.00
|
Mobilisation
IT
|
13/04/2012
|
£10075.00
|
Mobilisation
IT
|
18/05/2012
|
£9750.00
|
Mobilisation
IT
|
15/06/2012
|
£5200.00
|
Mobilisation
IT
|
18/07/2012
|
£3250.00
|
Mobilisation
IT
|
16/08/2012
|
£1950.00
|
Mobilisation
IT
|
06/09/2012
|
£650
|
Mobilisation
IT
|
Subtotal:
£56,005
The IT
consultancy role was commissioned to ensure fully functioning IT interfaces
between all contractors and Barnet Homes following the departure of the former
Barnet Homes Head of IT at a critical juncture in the mobilisation process.
Costs are based on an agreed day rate of £650.
v)
Miscellaneous
Date
|
Amount
(excl VAT)
|
Area
of work
|
26/10/2010
|
£2845.50
|
Advice
on emergency repairs cover
|
29/09/2011
|
£3360.00
|
Mobilisation
general
|
01/06/2012
|
£3500.00
|
Asset
Management Improvement Partnership joining fee and annual membership
|
20/07/2012
|
£350.00
|
Management
training
|
Subtotal:
£10,055.50
Echelon
provided advice on options for commissioning emergency cover for Barnet Homes
repairs services after our former repairs contractor, Connaught, went into
administration. The general mobilisation sum covers a further workshop with
Barnet Homes staff, staff from the successful contractors and residents
involved in the procurement process, along with associated reports.
Total
payments: £259,873.31 (excl VAT)
2. You
are welcome to view our hospitality and gifts register. Please contact the
Company to arrange an appointment.
Yours
sincerely
Barnet
Homes
18 September 12
Thank you for the lovely lists of payments which appear to
be fine.
The other part of my question was that I asked to see copy
contracts. Are there any formal written contracts with Echelon? and if there
are, please send copies to me with signatures redacted.
Yours sincerely
Mr Mustard
19
September 12
Dear Mr
Mustard
There were no formal written
contracts with Echelon
Yours sincerely
Barnet
Homes
8 October 12
Dear Barnet Homes
Sorry to keep asking
questions but this is an endlessly fascinating subject. I am sure we will reach
the end of the chain soon.
What items did you
benchmark and what against?
A simple list will suffice
as I do try not to ask overly long questions (or a copy of the benchmarking
paperwork if it can be easily copied without too many redactions).
Yours sincerely
Mr Mustard
5
November 12
Dear Mr
Mustard
In
response to your enquiry below, I will now provide the requested information.
Barnet Homes approached an
alternative supplier to quote for (ii) the Procurement Process.
We also
approached an alternative supplier to quote for iii) Mobilisation Project
Management.
Echelon
were appointed in both instances following receipt of the alternative quotes.
The appointment of Echelon for iv) IT consultancy was informed by the
alternative quote received for iii) Mobilisation Project Management.
Yours
sincerely
Barnet
Homes
So there you have it. A slap up meal and probably unlimited booze for 6 people in
Birmingham sits badly with over a quarter of a million pounds worth of work for
which only one alternative quote was obtained (and at least three written quotes
was the requirement at Barnet Council at that time) and for which there is no written contract recording
what exactly the terms are.
This terribly loose
arrangement should be giving kittens to senior management and internal auditors. They really ought to know about it already from internal controls and have
put a stop to it as well as any attendance
at Awards Dinners.
Yours frugally
Mr Mustard